Construction progress

Construction Progress: August - September 2024!

Friends, we’re pleased to share updates from the Enhance Bukovel construction site! In the past months, we’ve made significant progress, and here are the main highlights:

  • Completed the monolithic frames for the first three houses, with areas of 114 m², 120 m², and 120 m².
  • Started laying ceramic blocks for the interior and exterior walls.
  • Preparing for roof installation on the first and second houses.
  • Finalized the window installation project: we’ll be installing aluminum profile window systems to ensure excellent thermal insulation and a modern look.

We’re moving forward without pause, working to create your ideal cottage!